A smaller project, and challenging install, with fantastic results.

Pre-install
Many of the lights were failing in the factory and the output was poor.
What we did
We spent a significant amount of time working on the design and installation process. Reofab is a busy engineering factory meant working the weekend and using a massive boom lift to reach lights over permanent machinery and many tons of steel.
Outcome
A good little project that significantly increased lighting levels.

Working within a tight budget, we created a design to maximise lighting levels through clever placement and minimise operating costs.

Lighter installed ultra efficient LED highbays and automation, providing NZ Panels Auckland with exceptional yearly savings.
Lets Get Started